Chute liner wear map data mesh of casting
Case Studies

Wear analysis to extend life of coal chute liners

In conjunction with the customer, 7D Team developed the process, procedure and methodology to provide continuous wear monitoring statistical data that could be used to asses and predict wear characteristics, with a view to prolonging the life of the chute liners.

Corrosion on sea water pump
Case Studies

Reverse Engineering a Seawater Lift Pump

A Western Australian client had 2 stage bronze pump that was only lasting between 6 – 12 months, far less than the submersible motor which had a maintenance schedule of 4 years. They wanted to improve the pump life cycle in line with that of the submersible motor.